Construction Schedule

Print Friendly

20170515_ScheduleOverviewConstruction Schedule Overview – PDF

 

The first date for construction will be March 13, 2017.Β  The first work will include pavement crossovers and setting up traffic control. Utility work has started along South Street.

  1. On or after March 13, 2017 two lanes of traffic (one lane in each direction) will be put on the west side (existing southbound lanes).Β  This switch is so the Northbound lanes (east side) of Sagamore can be reconstructed.
  2. On or after March 20, 2017, Kossuth Street from Sagamore to Farabee will be under construction. Local traffic to businesses and residence will be maintained. No through traffic.
  3. On or after July 17, 2017, the intersection of South and Sagamore Parkway will be closed for a period of 28 days for reconstruction.Β  Not passable, completely shut down.
  4. On or after August 15, 2017, traffic (two way, one lane in each direction ) will be switched to the newly constructed lanes on the east side of Sagamore (northbound lanes), so the southbound lanes can be reconstructed.
    Kossuth Street from Sagamore to Farabee will be under construction, again. Local traffic to businesses and residence will be maintained. No through traffic.
  5. In December, 2017, all lanes of Sagamore will be open on new pavement for the winter.
  6. In March, 2018, the final work on the center medians will be done by lane restrictions. (The inside lanes would be intermittently closed and traffic would be north and sound bound in the outside lanes) Sagamore will be open to traffic.
  7. In March, 2018, work will begin on South Street. There will be closures to thru traffic on South Street with local business access maintained either from Sagamore or from the east and west on South Street.
  8. Project completion is anticipated to be July 2018